UK construction-safety guidance by the Riskora Editorial Team
Ground-borne vibration is the most under-assessed hazard in UK demolition. Cosmetic cracking in adjacent occupied buildings is what generates the complaints, the Section 80 abatement notices and the party-wall claims — and almost all of it could be predicted from a vibration risk assessment that actually engages with BS 7385-2 and BS 5228-2 rather than restating the standard's existence. The technical anchor is unambiguous: BS 7385-2:1993 sets the building-damage guide values for transient vibration (15 mm/s peak particle velocity at the foundation for residential reinforced/framed structures at 4 Hz rising with frequency, halved for unreinforced or light framed buildings, and a much lower threshold for historic or sensitive structures), and BS 5228-2:2009+A1:2014 Annex B provides predicted PPV ranges by demolition method. The risk assessment has to translate those values into a site-specific monitoring regime with trigger, action and stop levels — and tie each level to a named response. This page sets out what an inspector, a party-wall surveyor and a local-authority EHO expect to see.
Example Risk Assessment
Risk Assessment for Demolition Vibration Near Buildings — UK
No card required · 1 lifetime safety document · Upgrade when you need more
Required wherever demolition takes place within the predicted zone of influence of an occupied or sensitive structure — typically 25 m for hand demolition and concrete-cutting, 50 m for hydraulic breakers and pulverisers, and up to 100 m for ball-and-chain or explosive demolition (BS 5228-2 Annex B). Under CDM 2015 Reg 13 the principal contractor must plan, manage and monitor the work; under the Environmental Protection Act 1990 the local authority can serve a Section 80 abatement notice if vibration constitutes a statutory nuisance, and Section 61 of the Control of Pollution Act 1974 lets the contractor agree predicted limits with the EHO in advance. The Party Wall etc. Act 1996 will frequently apply where work is within 3 m or 6 m of a neighbour's structure. BS 6187:2011 (the demolition standard) requires the demolition engineer's plan to address vibration effects on adjacent structures. Insurers typically require pre-condition (dilapidation) surveys and continuous monitoring as a condition of cover.
A demolition contractor in Hull is taking down a 1950s 4-storey concrete-frame office bounded on three sides by occupied Victorian terraces. Using Riskora, the demolition engineer selects the Demolition preset and adds the vibration hazard. The risk assessment classifies the terraces as unreinforced masonry (BS 7385-2 guide value halved to 7.5 mm/s PPV at 4 Hz), predicts hydraulic-breaker PPV at the nearest terrace foundation at 4.8 mm/s using BS 5228-2 Annex B with the contractor's 850 kg breaker on stiff clay, and sets trigger / action / stop at 3.75 / 5.6 / 7.5 mm/s. Triaxial monitors are placed at the foundations of two index properties with real-time alerts to the site manager. A Section 61 consent was agreed with Hull City Council EHO at the lower of those limits. Pre-condition dilapidation surveys were completed for all six adjacent properties. The 14-page risk assessment exports in 8 minutes, the demolition runs for six weeks with two trigger-level alerts (both leading to a switch from hydraulic breaker to munching for that section), no action or stop breaches, and no damage claims at handover.
Select your trade, pick your hazards, and generate a structured document — no training required.
Create a demolition vibration risk assessment freeNo card required · 1 lifetime safety document · Paid tiers add branding, sign-off and audit trails
Or learn more about the platform: See plans and one-off options →
All documents should be reviewed by a competent person before use on site.
Generate a preview first. Sign up only when you want to save, edit or export.
Final RAMS must be reviewed and approved by a competent person before use.
Riskora is an assistive document preparation tool. All documents generated must be reviewed, verified, and approved by a competent person before use on site. Riskora does not replace professional safety judgment, and no output should be treated as a legal compliance guarantee.