Scaffold erection is skilled, high-risk work that requires a clear, step-by-step method statement. Falls during erection, structural failure from incorrect assembly, and dropped objects are constant hazards. If you are providing scaffolding services on a UK construction project, your method statement must demonstrate competence, planning, and NASC compliance.
Example Method Statement
Method Statement for Scaffold Erection — UK
No card required · 1 lifetime safety document · Upgrade when you need more
Under CDM 2015 and the Work at Height Regulations 2005, scaffold erection requires a written method statement describing the safe sequence of operations. NASC guidance (SG4:15) provides the industry standard for scaffold erection procedures. Principal contractors on commercial projects will require a method statement as part of the pre-start documentation. The method statement must be specific to the scaffold configuration, site conditions, and loading requirements.
A scaffolding company in Glasgow is erecting a 20-metre high independent tied scaffold on a city-centre commercial building. The scaffold will support multiple trades over a six-month refurbishment programme. The principal contractor requires a method statement covering erection, use, adaptation, and eventual dismantling. Using Riskora, the scaffold contracts manager generates a comprehensive method statement in minutes — covering SG4 compliance, tie patterns, advance guardrails, and handover procedures.
Select your trade, pick your hazards, and generate a structured document — no training required.
Create a scaffolding erection method statement freeNo card required · 1 lifetime safety document · Paid tiers add branding, sign-off and audit trails
Or learn more about the platform: See plans and one-off options →
All documents should be reviewed by a competent person before use on site.
Generate a preview first. Sign up only when you want to save, edit or export.
Final RAMS must be reviewed and approved by a competent person before use.
Riskora is an assistive document preparation tool. All documents generated must be reviewed, verified, and approved by a competent person before use on site. Riskora does not replace professional safety judgment, and no output should be treated as a legal compliance guarantee.