Buried Services RAMS for Groundworkers

UK trade-and-hazard guidance by the Riskora Editorial Team

A single buried-service strike can be fatal, can knock out hundreds of properties, and routinely costs six-figure sums in reinstatement and damages. HSG47 'Avoiding Danger from Underground Services' is the binding HSE guidance and a RAMS that does not name it will not pass review. The key shift HSG47 introduced is treating service location as a planned three-stage process — plan, locate, dig — rather than a one-off CAT scan at the start of the works.

Build RAMS for this trade and hazard

No account required for the preview · No card required

Regulations that apply

Construction (Design and Management) Regulations 2015

Regulation 22 (excavation)

Practical and appropriate steps to prevent danger to any person from an underground cable or other service.

HSG47 Avoiding Danger from Underground Services (3rd edition)

All sections

Three-stage approach: planning (drawings, utility enquiries via LSBUD/Mallatite), locating (CAT and Genny, vacuum excavation), and safe digging (hand-dig within 500mm of any indicated service).

Provision and Use of Work Equipment Regs 1998

Regulation 5

Excavator quick-hitches, bucket attachments and ground-engaging tools must be maintained — broken teeth and worn quick-hitches contribute to over-dig.

Hierarchy of controls for buried service strikes in groundworkers

Every UK RAMS reviewer applies the hierarchy of controls in the order below. Defaulting straight to PPE is the single most common reason a RAMS fails review.

1. Eliminate

Re-route the excavation to avoid known service corridors. Use trenchless techniques (directional drilling, mole) where alignment permits.

2. Substitute

Vacuum excavation in place of mechanical digging within 500mm of any indicated service.

3. Engineering controls

CAT4+ scanners with current calibration, Genny signal generator for traceable services, ground-penetrating radar for non-conductive services (water, drainage), service-marker tape detection.

4. Administrative controls

LSBUD utility search completed and drawings on site before any dig. Pre-start scan with CAT and Genny by competent operative (CSCS + utility detection training). Permit-to-dig issued by site supervisor. Hand-dig zone of 500mm around any indicated service, regardless of depth.

5. PPE (last line)

Hi-vis, helmet, gloves, safety boots. Insulated tools for any hand-dig near electric.

The most common rejection reason

Submitting a RAMS that names CAT scanning but does not specify the depth-of-cover assumption or the hand-dig boundary. 'CAT scan to be completed' is not a control — the hand-dig protocol around indicated services is what prevents the strike.

Example RAMS wording

An illustrative extract structured for principal-contractor review. Site-specific facts must be substituted and checked by a competent person.

LSBUD utility enquiry completed (reference LB2026-04-15-A). Drawings show 11kV electric, 75mm gas medium pressure and 100mm potable water in the works zone. Pre-start CAT4+ scan (calibration current to 12 March 2026) by trained operative will be supplemented with Genny signal injection on traceable services. Hand-dig only within 500mm of any indicated service, irrespective of depth on drawings. Vacuum excavation will be used to expose all services before mechanical excavation continues. Permit-to-dig issued daily by site supervisor and logged.

When to review this RAMS

  • Discovery of any service not shown on drawings
  • Damage to any service marker or warning tape during the dig
  • Loss of CAT scanner availability or out-of-calibration condition
  • Change of excavation alignment or depth
  • Any near-miss involving the excavator bucket

What to monitor on site

Daily CAT scanner pre-use check and battery test. Permit-to-dig signed at start of each shift. Photo log of exposed services. Toolbox talk before any change of dig position.

Frequently asked questions

Are utility drawings sufficient on their own?

No — HSG47 explicitly states drawings are a starting point only. Drawings can be wrong by metres in plan and significantly in depth, and many services (older mains, abandoned cables, private supplies) are not on any drawing at all.

What is LSBUD?

LinesearchbeforeUdig — a free online portal that checks proposed excavation locations against the asset records of around 110 utility owners. It does not cover every owner, so direct enquiries to local DNOs and water companies remain necessary.

How close can a mechanical excavator dig to a known service?

HSG47 sets 500mm as the hand-dig boundary around any indicated service, regardless of depth on the drawings. Most principal contractors enforce this strictly.