Utility workers face a unique buried-services problem: they are often the only contractor on site who knows their own asset is there, but everyone else's asset is the strike risk. NJUG (National Joint Utilities Group) Vol 1 and Vol 4 set the industry interface standards, and HSG47 Avoiding Danger from Underground Services applies to every dig. RAMS for utility installations must address not only the planned alignment but the risk of striking competing utilities at the crossings — which is where most strikes happen.

Build RAMS for this trade and hazard

No account required for the preview · No card required

Regulations that apply

HSG47 Avoiding Danger from Underground Services

All

Plan-locate-dig three-stage approach. CAT and Genny scanning. Hand-dig within 500mm of any indicated service.

New Roads and Street Works Act 1991

Section 81 (relations with utility undertakers)

Cooperation with other undertakers. Notice of works. Reinstatement specification.

NJUG Vol 1 (Guidelines on the Positioning and Colour Coding of Utilities Apparatus)

All

Standardised colour coding (red electric, yellow gas, blue water, green telecoms) and depth/positioning conventions for utility installations.

Hierarchy of controls for buried service strikes in utility workers

Every UK RAMS reviewer applies the hierarchy of controls in the order below. Defaulting straight to PPE is the single most common reason a RAMS fails review.

1. Eliminate

Trenchless installation (HDD, mole, pipe-bursting) where the utility being installed and the host ground permit. Avoids the open trench entirely.

2. Substitute

Vacuum excavation (e.g. RSP Mts Dino) within 500mm of any indicated service.

3. Engineering controls

CAT4+ and Genny set with current calibration. GPR for non-conductive crossings. Service-marker tape and warning slabs above the new install.

4. Administrative controls

LSBUD enquiry minimum 4 weeks before dig. Direct enquiry to local DNO and water company for any high-voltage or high-pressure crossing. Permit-to-dig per shift. NRSWA-trained supervisor on site.

5. PPE (last line)

Hi-vis Class 2, helmet, gloves, safety boots. Insulated tools for any hand-dig near electric.

The most common rejection reason

Failing to specifically address service crossings. Most strikes happen where the new utility crosses an existing one — not along the planned alignment. RAMS that address only the route and not the crossings will be rejected.

Example RAMS wording

An illustrative extract structured for principal-contractor review. Site-specific facts must be substituted and checked by a competent person.

Installation of 90mm SDR 11 PE water main from chamber W1 to W2 (alignment Drawing W-001 Rev C). LSBUD search ref LB2026-04-22-B identifies 4 utility crossings: 11kV electric (Western Power Distribution, drawing ref WPD-2024-887); 75mm gas medium pressure (Cadent, drawing ref CAD-2026-119); BT trunk (Openreach drawing OR-25-3340); existing 100mm asbestos cement potable water (UU drawing UU-22-665). Each crossing will be exposed by vacuum excavation before the new main reaches it. Hand-dig only within 500mm of any indicated service. Crossings will be photographed, depth recorded and detail-marked on as-built drawings. NJUG Vol 1 colour coding observed for all warning tape and slabs above the new installation.

When to review this RAMS

  • Discovery of any service not shown on LSBUD or direct enquiry response
  • Damage to any existing service
  • Change of installation depth or alignment
  • Loss of CAT scanner or vacuum excavator availability

What to monitor on site

Pre-shift CAT scanner calibration check. Permit-to-dig signed daily. Photo log of every exposed crossing. Toolbox talk before each new section of dig.

Frequently asked questions

Is LSBUD enough to find all buried services?

No — LSBUD covers around 110 utility owners but excludes many private supplies, abandoned cables and some smaller water and gas owners. Direct enquiry to the local DNO, gas distributor and water company supplements the LSBUD search.

What is the difference between Vol 1 and Vol 4?

NJUG Vol 1 sets positioning and colour coding for utilities. NJUG Vol 4 sets the safe-working interface between contractors of different utility owners — particularly important on jointed crossings.

Can vacuum excavators replace hand-dig?

Yes — vacuum excavation is recognised by HSG47 as a safer alternative to mechanical digging within the 500mm hand-dig zone. It is more expensive but faster than hand-dig and dramatically lower-risk.