Build your free safety document now
RAMS guide · United Kingdom · Updated May 2026

Demolition RAMS — UK contractor guide

Demolition is the highest-risk single trade in UK construction by hazard density — premature collapse, asbestos exposure, silica dust, falling debris and high-energy plant all operate concurrently. The legal framework is led by CDM 2015 (SI 2015/51), the Control of Asbestos Regulations 2012 (SI 2012/632) and the British Standard BS 6187:2011 (Code of practice for full and partial demolition). The single most-tested element on review is whether the document references a current refurbishment-and-demolition (R&D) asbestos survey.

R&D survey — non-negotiable for pre-2000 buildings

Under CAR 2012, a refurbishment-and-demolition survey is required before any demolition work on a pre-2000 building. The survey is intrusive, identifies and quantifies asbestos-containing materials, and the report is the document the demolition RAMS must reference. Without it, the work cannot legally start. Principal contractors will reject any demolition RAMS that does not cite the survey by reference number and date.

The survey distinguishes licensed work (sprayed asbestos, lagging, AIB in poor condition) from NNLW (notifiable non-licensed work) and non-licensed work. Licensed work must be done by a HSE-licensed contractor — the RAMS should name them. NNLW must be notified to HSE before work starts.

Structural sequence and BS 6187

BS 6187:2011 is the technical standard for the demolition sequence. The RAMS must reference a demolition method statement signed by a competent person (typically a chartered structural engineer or NDTG-qualified demolition supervisor) that walks through the structure from initial to final state, identifies the temporary instability windows, and names the controls (props, ties, exclusion zones).

Premature or uncontrolled collapse is the highest-consequence demolition failure mode. The sequence has to demonstrate that no operative or plant is in a position to be struck by a collapse at any point. For deconstruction projects (where the structure is taken down to be re-assembled), the sequence is the reverse-build of the original — even more critical to get right.

Dust suppression — silica, asbestos and general nuisance

The Workplace Exposure Limit (WEL) for respirable crystalline silica is 0.1 mg/m³ over 8 hours — a level that is exceeded almost immediately during any dry concrete or masonry breaking. The RAMS must name the controls: wet suppression at source, dust booms or sprays, RPE specification (FFP3 minimum, ideally powered air-purifying respirators for high-exposure tasks), and air monitoring where the WEL is foreseeable to be approached.

For asbestos work, dust controls are even more stringent — the asbestos plan of work (a separate document from the RAMS, required under CAR 2012 for licensed work) sets out the enclosure, decontamination unit (DCU) and clearance procedure. The RAMS should reference the plan of work, not duplicate it.

Public protection and the highway interface

Demolition almost always affects neighbours and frequently affects the public highway. The RAMS should describe the hoarding (BS 8408 specification typical), the exclusion zone (calculated from collapse-arc analysis, not estimated), the pedestrian diversion arrangements, and the traffic management plan for waste removal. For demolition within 6m of an occupied building, party-wall awards under the Party Wall etc. Act 1996 will normally apply — the RAMS should reference the award and any conditions.

Hazards specific to demolition

Each hazard paired with the UK regulation or HSE guidance document that applies.

  • Premature or uncontrolled structural collapse

    BS 6187 + CDM 2015

  • Asbestos exposure during disturbance of ACMs

    CAR 2012 + L143

  • Silica dust from concrete / masonry breaking

    COSHH 2002 + WEL

  • Falling debris struck against operatives below

    CDM 2015 + WAHR 2005

  • Underground service strike during slab / foundation removal

    HSG47

  • Plant interface — high-reach excavator slewing radius

    HSG144

  • Noise and vibration nuisance to neighbours

    Noise at Work Regs 2005 + EPA 1990

  • Fire risk from hot cutting of structural steel

    FPA HW01 + RRO 2005

Most common rejection reasons

Patterns we see when principal contractors send demolition RAMS back for re-work.

  1. No reference to a current R&D asbestos survey for any pre-2000 building.
  2. Demolition method statement not signed by a competent person, or sequence not described.
  3. Silica dust controls limited to 'water suppression' — no RPE category, no WEL discussion, no monitoring.
  4. Exclusion zone given as a distance without showing the collapse-arc calculation.
  5. No reference to the asbestos plan of work for any licensed asbestos in scope.

What a compliant demolition RAMS must include

  • R&D survey reference number, date and surveyor
  • Demolition method statement reference (BS 6187) and competent person's signature
  • Structural sequence with temporary instability windows named
  • Silica / dust control schedule with RPE specification
  • Asbestos plan of work reference (separate document)
  • Exclusion zone calculation
  • Hoarding specification (BS 8408)
  • Plant inventory with operator competence (CPCS demolition card grades)
  • Waste segregation, transfer notes, hazardous waste consignment notes
  • Sign-off block

Relevant regulations and HSE guidance

The legal framework a demolition RAMS operates inside — all links point to the official source.

Demolition RAMS — frequently asked questions

What's the difference between an R&D survey and a management survey?

A management survey is a non-intrusive check to support ongoing management of asbestos in a building in use. An R&D (refurbishment and demolition) survey is intrusive — surveyors break into walls, ceilings, floors and voids to find and quantify all ACMs that will be disturbed by the planned work. Only an R&D survey is acceptable for demolition. CAR 2012 reg 5 requires this before work starts.

Do I need to notify HSE before demolition work?

Two separate notifications can apply. CDM 2015 notification (F10) is required for projects over 30 days with more than 20 workers, or over 500 person-days. Asbestos notification (ASB5) is required for any licensed asbestos work and 14 days' notice is the minimum. NNLW (notifiable non-licensed work) also requires notification using ASB5.

What competence card do demolition operatives need?

CCDO (Certificate of Competence for Demolition Operatives) cards issued by the NDTG are the demolition industry's competence standard. They run from Trainee through Operative, Topman, Advanced Topman to Supervisor and Site Manager. The RAMS should name the card grade for each operative. CSCS cards are not sufficient for demolition-specific work.

How is the exclusion zone calculated?

By collapse-arc analysis — a calculation of where debris could fall during controlled collapse. The base distance is at least equal to the height of the structure being demolished, with adjustments for wind, projectile risk and any directional controls (water cannons, dust booms). The competent person who signs the method statement should also document the exclusion zone calculation.

Can soft strip happen at the same time as structural demolition?

Only with strict segregation. Soft strip (removal of fixtures, services, non-structural elements) creates dust, manual handling and asbestos risks of its own. Doing it in parallel with structural demolition is sometimes unavoidable on programme but the RAMS must show how the two activities are physically separated — typically by floor, with no operative working below an area being structurally demolished.

Demolition RAMS by UK city

City-specific local context — council, HSE office and local building stock notes — for demolition contractors.

Local context for demolition work in other UK cities

Riskora prompts for the council permits, building stock and access constraints that apply wherever the job is — these are the demolition details principal contractors check first in each city.

Demolition RAMS in London · Greater London
Dense Victorian and Georgian terrace stock, listed-building prevalence in central boroughs, deep basements driven by floor-area constraints, and a high proportion of refurbishment-over-new-build. London ground conditions vary sharply between London Clay (most of the centre and north), gravel terraces along the Thames, and chalk in outer south-east boroughs. Permits and conditions run through London borough councils (building control varies by borough). All RAMS guides for London
Demolition RAMS in Birmingham · West Midlands
Significant interwar and post-war stock, large industrial and warehouse buildings around the Jewellery Quarter and Digbeth, and a heavy current refurbishment programme in the city core. Ground conditions vary between Mercia Mudstone in the centre and glacial sands and gravels in outer areas. Permits and conditions run through Birmingham City Council Planning & Building Control. All RAMS guides for Birmingham
Demolition RAMS in Leeds · West Yorkshire
Heavy Victorian commercial stock, Yorkshire stone construction with specific stone-cleaning and lime-mortar considerations, large 1960s/70s office towers undergoing refurbishment, and modern build-to-rent towers concentrated south of the river. Permits and conditions run through Leeds City Council Building Control. All RAMS guides for Leeds
Demolition RAMS in Glasgow · Greater Glasgow
Iconic Glasgow tenement stock — sandstone, four storeys, common closes — with associated party-wall, common-stair and lime-mortar challenges. Significant industrial heritage in Govan, Maryhill and Springburn. Modern stock concentrated in the merchant city and west end. Permits and conditions run through Glasgow City Council Building Standards (Scotland uses Building Standards, not Building Control). All RAMS guides for Glasgow
Demolition RAMS in Edinburgh · Edinburgh & Lothians
Georgian New Town stock with strict listing controls, mediaeval Old Town with severe access constraints (closes, narrow wynds, multi-level frontages), and tenement stock in the south and west. Sandstone façades require lime-based mortars and trained stonemasons. Permits and conditions run through City of Edinburgh Council Building Standards. All RAMS guides for Edinburgh
Demolition RAMS in Bristol · South-West England
Bath stone and Pennant sandstone façades, Victorian terraces concentrated in Clifton, Redland and Southville, post-war estates undergoing regeneration, and a high proportion of harbourside conversions on former dock land. Permits and conditions run through Bristol City Council Building Control. All RAMS guides for Bristol
Demolition RAMS in Liverpool · Merseyside
Heavy Victorian commercial stock, Georgian and early Victorian terraces in the canning area, large warehouse buildings in the Baltic Triangle, and significant interwar and post-war housing across outer wards. Ground conditions are dominated by sandstone close to the centre. Permits and conditions run through Liverpool City Council Building Control. All RAMS guides for Liverpool
Demolition RAMS in Cardiff · South Wales
Pennant sandstone Victorian terraces in Cathays, Roath and Canton; modern apartment stock in Cardiff Bay; and significant 1960s/70s office buildings across the central core. Ground conditions include reclaimed dock land in the Bay area and Triassic mudstones across the centre. Permits and conditions run through Cardiff Council Building Control. All RAMS guides for Cardiff
Demolition RAMS in Sheffield · South Yorkshire
Stone-built Victorian terraces, heavy industrial stock in Kelham Island and the Don Valley, post-war flats undergoing demolition or refurbishment, and modern build-to-rent around the city centre. Ground conditions include made-ground from former industrial use across much of the lower Don Valley. Permits and conditions run through Sheffield City Council Building Control. All RAMS guides for Sheffield
Free RAMS builder

Create your RAMS free — preview before sign-up

Generate a preview first. Sign up only when you want to save, edit or export.

Final RAMS must be reviewed and approved by a competent person before use.