Regulation and guidance referenced
CDM 2015 Regulation 20 — Construction phase plan and pre-construction information (HSE)
The demolition method statement is the operational expression of the construction phase plan — it must reference the PCI and the structural pre-demolition survey.
BS 6187:2011 — Code of practice for full and partial demolition (BSI)
Defines the sequence: refurbishment and asset reclaim → soft strip → structural demolition. Method statements should cite which BS 6187 method (top-down, deliberate collapse, push/pull, balling, wire rope) is used and why.
HSG150 — Health and safety in construction (HSE)
Sets the baseline competence, supervision and welfare expectations the demolition method statement must satisfy.
Regulation 6 CAR 2012 — Asbestos identification before refurbishment / demolition (HSE)
Refurbishment and demolition survey must be in place — the method statement should name the survey reference and date.
Common mistakes that get this document rejected
No structural pre-demolition survey reference
Without a named structural engineer's survey and sequence, the document fails CDM 2015 information transfer and BS 6187. Principal contractors will reject on this alone.
Asbestos R&D survey not cited
Even with a survey done, the method statement has to reference the survey number, date and any positive locations with their planned removal method before structural works.
Exclusion zones described in words only
Drop zones, exclusion zones and pedestrian routes need a marked drawing or marked-up site plan — narrative descriptions are routinely rejected.
Worked example
Scenario: Partial demolition of a two-storey end-of-terrace shop to enable a new build behind a retained façade.
What went wrong: Initial method statement was rejected for missing the temporary works design for the façade retention, no sequence reference to BS 6187, and the asbestos R&D survey referenced as 'on file' rather than by survey number.
The fix: Rebuilt with named TWD reference, BS 6187 top-down sequence with hand demolition floor-by-floor down to slab, R&D survey number and positive locations called out, drop zones on a marked site plan, and dust/noise controls per HSG150.
Outcome: Accepted on second submission. Method statement issued with the construction phase plan and copied to the demolition surveyor.