RAMS for Earthworks UK | Bulk Excavation, Fill & Compaction

Generate a UK-structured RAMS for earthworks — bulk excavation, fill placement and compaction. Covers temporary works, plant interface, slope stability, dust, noise and contaminated land.

Frequently asked questions

When does earthworks need a Temporary Works Coordinator?
Effectively always on commercial and infrastructure work. Any unsupported slope, batter or bench higher than around 1.2m is a temporary works item requiring competent design and a TWC sign-off. The RAMS references the TWR entry.
How is plant-pedestrian segregation handled?
The segregation plan defines exclusion zones around operating plant (typically the slew radius plus 0.5m buffer), pedestrian-only walking routes, banksman positioning, and the eye-contact rule before entering a plant area. This is the single most important control on most earthworks sites.
What about contaminated land?
Where the site investigation has identified contamination above generic assessment criteria, the RAMS includes additional COSHH controls — RPE selection, decontamination procedures, PPE doffing arrangements, and disposal routes for arisings. This is treated as a separate method-statement section.
Will this satisfy a Tier 1 contractor on a major project?
Yes. The format and content match what HS2, the Tier 1 housebuilders, and the major civils contractors expect. Site-specific TWC names and TWR references are added in the project-details section before submission.